Last line connecting ZNPP to energy system of Ukraine cut off

На ЗАЕС відключили останню лінію, що з’єднувалася з енергосистемою України

As a result of a fire caused by Russian shelling of the Zaporizhzhia Nuclear Power Plant (ZNPP), the last line connecting the ZNPP/ZTPP (Thermoelectric Power Plant) node to Ukraine’s power grid has been disconnected.

Source: Energoatom

Quote: “Today, 5 September, 2022, as a result of the fire that occurred due to shelling, the 330 kW ZTPP-Ferro-alloy power line was disconnected, that is, the last line that connected the ZNPP/ZTPP node with the energy system of Ukraine!

As a result, the 6th power unit was unloaded and disconnected from the grid, which currently supplies the ZNPP’s own needs.”

Details: Energoatom notes that over the past three days, Russian occupying forces have been fiercely shelling the area around the ZNPP.

As a result, the 750 kW ZNPP – Dniprovska, 330 kW ZTPP – Kakhovska and 330 kW ZTPP – Melitopol power lines were damaged and disconnected. The 750/330 kW JSC ZNPP was damaged.

Other power lines of the ZNPP/ZTPP complex were damaged earlier.

Source: Ukrainian pravda

Link: https://www.pravda.com.ua/news/2022/09/5/7366161/

To top